|
Main
Page 
Preface
The Resource Coordination Policy
Committee
How Our Flood Problems Developed
Existing Services and Programs
Federal Programs
State Programs
Chicago
County-wide
Stormwater Programs
Watersheds
Of The Chicago Metropolitan Area
Where To Go For More Information
Glossary
Cooperating Agencies and Municipalities
Contact Webmaster 
|
 |
State Programs
Illinois
Department of Natural Resources, Office of Water Resources
Flood Control Planning
The Flood Control Act of 1945, 615 ILCS 15, gives the Office of Water Resources
(OWR) legal authority to participate in the improvement of the rivers of
the State for the purpose of regulating and controlling flood and low-water
flows. Criteria followed by the Office relating to flood control planning
include:
• Assurance that the most severely damaged
areas receive priority consideration and assistance from State and Federal
sources.
• State water resource projects be designed
to maximize economic efficiency at minimal environmental impact.
• State expenditures result in the maximum
benefits for the least possible cost.
• Local interest and investment of funds be
required as evidence of involvement in any project.
OWR, through its regular flood control program and in cooperation with
local governmental sponsors, has provided over 5350 acre-feet of floodwater
storage in eleven reservoirs, as well as improved channels at numerous
locations throughout the Chicago Metropolitan Area.
OWR provides funding through its Small Projects Program to alleviate smaller,
more easily solvable flood problems. Maximum OWR funding is currently $75,000
per Small Project. Additionally, OWR provides study/project support through
field activities including the operation of a modernized water resources
data collection network and the acquisition of field survey data.
OWR participates in Federal programs within the legal authority of State
Statutes. OWR is an active sponsor, along with other regional and local
agencies, of floodwater management plans developed with NRCS, MWRD, and
Corps of Engineers assistance. Sponsor responsibilities include land acquisition
needed for the structural measures and implementation of various non-structural
programs and project operations and maintenance.
Stream Preservation Program
OWR assumed responsibility for the development of a stream preservation
program as a part of the non-structural program of the Chicago Metropolitan
River Basin Plans.
Stream Preservation refers to the management of a stream’s conveyance capacity
and can include natural channels and environmental enhancements.
It includes the following goals and objectives:
• Keep debris, sediment, and restrictive vegetation
out of rivers and streams.
• Convey floodwater safely through each community.
• Assure that flood control structural measures
will perform as planned by maintaining unobstructed inflows and outflows.
• Provide for annual inspection and maintenance
of the key rivers and streams in each watershed.
• Encourage each community to assume responsibility
for maintenance of the stream portion within its jurisdiction.
• Provide assistance and advice to communities
and other regional agencies when needed.
• Encourage environmental awareness of the
general public.
The program has been implemented and coordinated through each respective
watershed steering committee. Greater community compliance with this program
would provide even greater results.
State Floodplain Regulations
The Rivers, Lakes, and Streams Act, 615 ILCS 5, gives the Office of Water
Resources the authority to regulate construction activities within the
floodway. The floodway is that portion of the floodplain required to store
and convey floodwater. A permit is required to construct within the floodway.
Construction that significantly raises the stage or velocity of the 100-year
projected flood in the floodway is prohibited . Only appropriate uses are
allowed.
The Office has compiled an official list of designated regulatory floodway
maps. Information is available from the Office or from the local municipality.
Floodproofing and Flood Insurance Programs
The Office’s Floodplain Management Section is the State Coordinating Agency
for the National Flood Insurance Program. This section provides advice
and information concerning the flood insurance program as well as technical
assistance.
Flood Mitigation Program
Illinois Revised Statutes, Chapter 19, para. 126d. gives the Office of
Water Resources the authority to acquire floodplain property to convert
to public use. This authority is used to acquire properties that cannot
be protected by flood control structures, or where structural flood control
measures are not practical or economically feasible. Only those communities
participating in the National Flood Insurance Program may be considered
for funding through this program. Currently, four communities in DuPage
County (Addison, Elmhurst, Oak Brook, and Wood Dale) are receiving flood
mitigation project funding. In Will County a mitigation project was funded
by OWR as the result of the 1990 Plainfield tornado.
The Office of Water Resources also provides technical mitigation and floodproofing
assistance to property owners through publications available free of charge.
Metropolitan
Water Reclamation District of Greater Chicago
The first major modification of the natural drainage system in the Chicago
Metropolitan Area was made by the Metropolitan Water Reclamation District (MWRD) in the late 1880’s. A series of canals were constructed to reverse
the flow of the Chicago River and carry waste away from Lake Michigan.
The existing canal systems (Sanitary and Ship Canal, North Shore Channel,
and Calumet-Sag Channel) provide a substantial volume of flood control
storage and flow capacity. The water level in the waterways can be lowered
in anticipation of a storm to provide stream bank storage of up to 4,600
acre-feet of additional capacity beyond normal operating water levels.
Flood Control Program
While MWRD does not have a specific statutory responsibility in the area
of flood control, its involvement and expertise in the areas of water pollution
control and drainage have led the MWRD to assume a flood control leadership
role in the Metropolitan Area.
By the mid-1960’s, MWRD was involved in the design and construction of
many flood control storage reservoirs and stream improvement projects.
Melvina Ditch Reservoir, completed early in 1967 in Oak Lawn, was the first
reservoir constructed. To date 30 reservoirs have been completed with MWRD
participation. These reservoirs range in capacity from 24 to 1,089 acre-feet
of stormwater detention and provide flood relief to thousands of people.
Most of the reservoirs designed by the Water Reclamation District will
accommodate a 5- to 6-inch rainfall storm event.
The maintenance and operation responsibility of approximately one third
of the existing reservoirs has been fully undertaken by the local municipalities.
MWRD shares this responsibility with a local public entity in one third,
and the remaining one third are maintained solely by the MWRD.
MWRD has sought Federal, State, and local participation in its flood control
efforts. MWRD was one of the principal sponsors of the floodwater management
plans developed by the Natural Resources Conservation Service. These plans
address flood control on a regional basis, and most of the reservoirs delineated
by these plans have been completed and are operating.
MWRD, as a local sponsor of the NRCS watershed projects, was responsible
for the acquisition of land rights and contract administration. Since the
inception of this program, MWRD has expended more than $10,000,000 in land
rights acquisition for five reservoirs (Structures 2, 3, 4, 5, and 6) in
the Upper Salt Creek Watershed, more than $15,000,000 for three reservoirs
(Structures 32, 53, and 143) in the Little Calumet River Watershed, and
more than $2,000,000 for two reservoirs (Structures 86 and 102) in the
lower Des Plaines Watershed. As contracting agent, MWRD has administered
the construction of ten reservoirs with NRCS funding.
In 1974, MWRD adopted ‘‘Flood Control Program Guidelines’’ (amended January
1981), which established certain criteria for MWRD’s participation in proposed
local flood control reservoir projects (projects not addressed in the regional
NRCS plans). These criteria included such items as the requirement for
a local sponsor to share the costs of reservoir implementation, a requirement
that the proposed reservoir be of at least 100 acre-feet capacity, that
the flooding problem be of long standing, and that the project has a favorable
benefit/cost ratio.
The January 1981 amendment requires a ‘‘Strategic Planning Study for Flood
Control’’ to be conducted by the Illinois Office of Water Resources (OWR).
This OWR study is required for possible State and MWRD funding of the project
and is used to define a cost effective project. The cost of a State and
MWRD study is borne equally by the local sponsor and the Water Reclamation
District. The Flood Control Program Guidelines ensure that public funds
are expended only in situations where serious flooding problems exist and
adequate justification of expenditures is made.
State legislation is currently being considered that would name the MWRD
as the Regional Stormwater Management Agency for Cook County. The MWRD
would be involved in the planning and design of flood control facilities
and provide low interest loans for approved projects.
MWRD Sewer Permit Ordinance
Since 1972, detention of stormwater runoff has been a requirement of the
sewer permits within the service area of the MWRD. This area includes most
of Cook County.
The intent of the ordinance is to require local governments and developers
to jointly provide detention storage. This eliminates excessive runoff
during heavy storm periods and promotes comprehensive community-wide programs
for flood control. The MWRD ordinance requires that the release rate of
stormwater runoff from a development not exceed stormwater runoff from
the area in its undeveloped state.
Infiltration/Inflow Corrective Action Program (ICAP)
The Clean Water Act enacted by Congress mandated that all sanitary sewer
systems in the USA be rehabilitated to eliminate excessive stormwater.
In the Metropolitan Water Reclamation District of Greater Chicago (MWRDGC)
area, regional sewer conferences were convened. As a result of these conferences,
a Sewer Summit Agreement was created which was acceptable to all municipalities.
The Sewer Summit Agreement enabled the local municipalities to meet the
requirements of the Clean Water Act without creating a financial burden
on the local taxpayers.
The purpose of ICAP, as developed by the local communities, is to remove
excessive Infiltration and Inflow (I/I) from sanitary sewers in order to
meet the following goals:
• Eliminate basement sewer backups and other
conditions that cause health hazards or financial losses.
• Prevent pollution of the waterways.
On November 21, 1985, the MWRDGC’s Board of Commissioners approved adoption
of the Sewer Summit Agreement and authorized an amendment to article 6-5
of the Manual of Procedures for the Administration of the Sewer Permit
Ordinance, creating ICAP.
Sanitary sewers are designed and intended to convey only sanitary wastewater.
The major sources of stormwater entering a sanitary sewer system are excessive
I/I. Infiltration is the stormwater entering a sanitary sewer system through
defective pipes, pipe joints, pipe connections, and manhole walls. Inflow
is the stormwater discharged into a sanitary sewer system through roof
leaders, cellar drains, yard and area drains, foundation drains, cooling
water discharges, drains from springs and swampy areas, manhole covers,
and cross connections from storm sewers and combined sewers.
Excessive I/I overloads sewers. Overloaded sewers cause basement flooding,
health hazards, financial losses, and inconvenience to residents and businesses.
Excessive I/I also results in additional sewage treatment costs to the
public.
Tunnel and Reservoir Plan (TARP)
The Chicago Metropolitan Area has two different methods for collecting
sewage. Flood problems in areas serviced by these two systems must be resolved
differently. In most areas, except the central basin, sewage and storm-
water are collected in different sewers. One system of sewers collects
stormwater, and the other system of sewers collects sewage. These areas
are commonly called ‘‘separate sewer’’ areas. Surface flood retention reservoirs,
mentioned previously, are provided only in separate sewered areas. In the
central basin, sewage and stormwater are collected in the same sewer and
the areas served are called ‘‘combined sewer’’ areas. Combined sewer areas
comprise 375 square miles of the total 872 square mile area under the jurisdiction
of the Water Reclamation District. Flood and pollution problems in these
areas are handled with combined sewers by the Tunnel and Reservoir Plan
(TARP). The TARP service area includes the City of Chicago and 51 suburban
municipalities.
TARP consists of two phases. Phase I of the Plan is primarily a water pollution
control project. Phase II is associated primarily with urban flood control.
Virtually all excess combined sewage will be captured by the ultimate tunnel-reservoir
system. In addition, waterway stages will be controlled, reducing overbank
flooding, basement flooding, and bypassing of raw sewage to Lake Michigan.
|